Azerbaijan reveals current state of ongoing road infrastructure projects in the Karabakh

Azerbaijan reveals current state of ongoing road infrastructure projects in the Karabakh

The State Agency of Azerbaijan Automobile Roads has shared information on current road infrastructure projects in the Karabakh and East Zangezur economic regions.

"The construction of the "Victory Road" with a length of 101.5 kilometres has been fully completed," the agency noted.

Ahmadbayli-Fuzuli-Shusha highway

Technical indicators: length 81.6 kilometres, I technical category, four lanes.

The construction of an earthen embankment has been completed on sections 0-17, 32-36, 40-42, 51- 52, 58-63, 70-71 kilometres, construction of bridges continues at 1, 27, 34, 37 and 50 kilometres, construction of tunnels and underpasses - at the 80th and 81st kilometres

Toganali-Kalbajar-Istisu highway

Technical indicators: length 80.7 kilometres, I-II technical categories, 2-3 lanes, tunnel length - 11.6 kilometres.

An asphalt concrete pavement was applied to a 7-kilometer country road to Toganali, a 48-kilometer existing road was expanded and prepared for operation, an asphalt-concrete pavement was applied to a 14-kilometer section of the road, excavation work continues in the tunnel through Murovdag.

Kalbajar-Lachin highway

Technical indicators: length 72.3 kilometres, I-II technical categories, 2-3 lanes, tunnel length - 9.8 kilometres.

Work on the construction of the roadbed of the road has been completed by 10 percent.

Construction of road infrastructure in the Kalbajar and Lachin districts

Technical indicators: length 30 kilometres, IV technical category, two lanes.

Work is underway to build an earthen embankment and pavement, the construction of drainage systems has been completed by 95%, 80% of road signs have been installed.

Horadiz-Jabrayil-Zangilan-Aghbend highway

Technical indicators: length 123.8 kilometres, I technical category, 4-6 lanes.

The construction of the roadbed is underway on sections 0-23, 50-66th kilometre. Earthworks were completed by 17%, the construction of drainage systems and crossings - by 12%, bridges - by 10%.

Khudafarin-Gubadli-Lachin highway

Technical indicators: length 70.4 kilometres, I technical category, four lanes.

A subgrade was built on the 0-37th kilometer section in the direction of Gubadli-Lachin, on the 0-1 and 5-14th kilometre sections in the direction of Khanlyg, work is underway on the construction of bridges, topographic work at the 1st and 22nd kilometres. Earthworks were completed by 36%, pavement construction - by five%, drainage systems and crossings - by 37%, bridges - by 29%.

Gubadli-Eyvazli highway

Technical indicators: length 26 kilometres, IV technical category, two lanes.

The construction of an earthen embankment on the road to the Eyvazli village in the Gubadli district is underway. Work has been completed to widen and bring the roadbed to the standard width at the 8th kilometre of the road.

Shukurbeyli-Jabrayil-Hadrut highway

Technical indicators: length 43 kilometres, I technical category, four lanes.

Earthworks were completed by 51 percent, pavement construction - by nine percent, drainage systems and crossings - by 52%, bridges - by 49%.

Fuzuli-Hadrut highway

Technical indicators: length 13 kilometres, I technical category, four lanes.

Work is underway on the construction of the roadbed; excavation work has been completed on the 1-5th kilometre section and the construction of the roadway has been completed by 50%.

Barda-Agdam highway

Technical indicators: length 45 kilometres, I technical category, four lanes.

Earthworks were completed by 42.5%, pavement construction - by 6.8%, drainage systems and crossings - by 28.2%, bridges - by 81.2%.

Talish-Tapgaragoyunlu-Gashalty-Naftalan highway

Technical indicators: length 22 kilometres, II-IV technical categories, two lanes.

The 0-6th kilometre section has been cleared of mines and unexploded ordnance, a subgrade, drainage systems and a road base have been built. Asphalt concrete was applied on the 0-1.8-kilometre section, and the deformed road surface was removed on the 15–22-kilometre section.

3241 Mal angesehen

ARTICLES IN ENGLISH»



MEISTGELESEN



AKTUELLES



OPINION



Call for Contributors: Caucasus Watch is looking for experts, journalists and fact-checking specialists!

“Caucasus Watch” is seeking local specialists from Georgia, Armenia, Azerbaijan and the North Caucasus region, to assist our research endeavours and help enrich our content.

“Caucasus Watch” is an independent platform, which provides coverage of recent developments in various locations of the Caucasus region for the German and overall European stakeholders. We are an international team of Caucasus enthusiasts and are currently looking for local contributors who focus on social, economic, political and security dynamics of the said region.

The platform offers: I) a flexible format of cooperation, as well as competitive remuneration; II) access to English and German speaking readership in the wider European region; III) an opportunity to join the network of regional specialists through the initiatives and events to be organized by the Caucasus Watch and partner institutions.

Interested individuals are asked to provide a CV and a cover letter along with an abstract or a writing sample (in English or German), to the following address: redaktion@caucasuswatch.de.

Additional questions can be directed to Igor Dostalik through: i.dostalik@caucasuswatch.de.